[Sep.2020] ECOGARDEN PROJECT UPDATE
Ecogarden project progress – September, 2020
I. Juridical
- Adjustment of local planning 1/1500 has been approved by the Department of Construction of Thua Thien Hue province and is submitted to the Provincial People's Committee for approval.
II. Construction
- TT2 road - the main road of the project is completed 90%
- Landscape bridge and gate: 50% completed
- Camellia area: Completed 80% of technical infrastructure, electricity and water, internal roads.
III. Some latest images of the project
Great Ecogarden site viewed from above
TT2 road at night
The landscape bridge is under construction
Area Square