[March 2021] UPDATE PROGRESS OF ECOGARDEN PROJECT
I. Construction:
• Complete 90% of the entire road TT2 landscape culvert, landscape bridge No.02, national school gate.
• Complete the green landscape of the Square and CC02 lake park, TT2 route, East-West lake.
• Road TT3: Construction of K90, K98 and crushed stone is in progress.
• Leveling: Completed 55% of the entire project.
II. Some recent pictures of the project:

• Complete 90% of the entire road TT2 landscape culvert, landscape bridge No.02, national school gate.
• Complete the green landscape of the Square and CC02 lake park, TT2 route, East-West lake.
• Road TT3: Construction of K90, K98 and crushed stone is in progress.
• Leveling: Completed 55% of the entire project.
II. Some recent pictures of the project:

Square area
Landscape Bridge


Project overview